A typical payment schedule
Every developer sets their own, but this pattern is common on the Costa del Sol. Example: a €500,000 new-build apartment, with 10% IVA added to each payment.
| Stage | When | Share | You send (incl. IVA) |
|---|---|---|---|
| Reservation | Day 1 | €10,000 | €11,000 |
| Private purchase contract | About 30 days later | 20% less reservation | €99,000 |
| Construction stage 1 | Often 6–9 months in | 10% | €55,000 |
| Construction stage 2 | Often 12–18 months in | 10% | €55,000 |
| Completion at the notary | 18–24 months in | 60% | €330,000 |
That's €550,000 over roughly two years, plus 1.2% stamp duty (AJD), notary, Land Registry and lawyer at the end. At €1.15 per £1 the whole schedule costs about £478,000. If you have a mortgage, it normally replaces part of the completion payment.
Check the guarantee before every payment
Spanish law requires developers to protect money paid before completion with an individual bank guarantee (aval bancario) or insurance policy in your name, and to pay it into a special account. If the building isn't finished or the licence isn't granted, the guarantee repays you.
- Your lawyer should obtain the guarantee certificate for each payment before you send it.
- Pay only into the account named in the contract and the guarantee, and confirm it by phone.
- Keep every transfer confirmation. You'll need them to claim on the guarantee, and for the deed at completion.
Why the exchange rate matters more on a new build
The euro price is fixed when you sign. What it costs you in pounds, kronor or dollars is not, and you're exposed for much longer than on a resale. On the €330,000 completion payment above:
| Rate at completion | Cost in pounds | Compared with today |
|---|---|---|
| €1.08 per £1 | £305,556 | £18,599 more |
| €1.15 per £1 (today, in this example) | £286,957 | No change |
| €1.22 per £1 | £270,492 | £16,465 less |
Swings like that over two years are not unusual. If your budget can't absorb the bad case, you need a plan for each payment.
Three ways to manage it
Fix each stage with a forward contract
Forward contracts commonly run up to 12 months, sometimes longer. You can fix the stage payments that fall within range now and fix later ones as they come into range. If the developer's dates slip, which they often do, a window forward lets you take the money any time within a period. How forward contracts work →
Convert early and hold euros
Convert some or all of the money now and hold it in a euro account until each payment is due. It removes the rate risk entirely, but the money sits in euros, and you lose any benefit if the rate improves.
Mix the two
Many buyers fix or convert enough to cover the deposit and stage payments, then decide on the completion payment closer to the time, especially if a mortgage will cover part of it.
Get a specialist quote
Ask a specialist to plan your stage payments around the developer's schedule. No obligation.
Get a currency quoteWe may receive a commission if you go ahead.
Money guides
- Sending money to Spain to buy property
- What is my bank really charging? (calculator)
- Fixing your exchange rate: forward contracts
- How the completion payment works at the notary
- Mortgage, bills and pension payments to Spain
- Moving to Spain with your UK house sale money
- Buying with Swedish, Norwegian or Danish kroner
- Selling up: the 3% retention and bringing money home
- Inherited a Spanish property? Tax, selling, money
Related guides
Frequently asked questions
Are off-plan stage payments in Spain protected?
Yes, if they are handled correctly. Spanish law requires developers to guarantee money paid before completion with an individual bank guarantee or insurance policy for each buyer, and to pay it into a special account. Your lawyer should obtain the guarantee certificate for every payment before you send it.
Do I pay IVA on off-plan stage payments?
Yes. IVA (VAT) at 10% is charged on each payment to the developer as it is made, not only at completion, so every transfer you send needs to include it. Stamp duty (AJD, 1.2% in Andalucía) is paid at completion.
Can I fix the exchange rate for all my off-plan payments?
Partly. Forward contracts commonly run up to 12 months, sometimes longer, so near-term stage payments can be fixed now and later ones fixed as they come into range. Some buyers instead convert early and hold euros, which removes the rate risk but ties the money up.